Harris Homestead

Wednesday, June 14, 2006

Index

Calendar

May 1
May 5
May 12
May 16
May 17
May 18
May 20
May 22
May 24
May 27
May 30
May 31

Jun 3
Jun 7
Jun 9
Jun 12
Jun 14
Jun 17
Jun 19
Jun 21
Jun 23
Jun 27
Jun 30

Jul 1
Jul 5
Jul 8
Jul 10
Jul 12
Jul 15
Jul 17
Jul 18
Jul 20
Jul 25
Jul 27

Aug 1
Aug 2

Skating (Dec)

Dec 10 (bird feeding)

Dec 31 snow

 

Leona and Robin to site to talk with duct people and electrician - very, very worthwhile meetings.
 
Plumbing also started (probably late Tuesday).
This is in the laundry room (hot and cold water supply).
 
Electrician's vehicle.
Father and son team.
 
Electrician (father) in second floor hallway talking to Leona - very nice man.
(with tub in background)
 
North side.
Electrical meter panel installed at left side.
 
Electrical panel about to be installed in furnace room.
 
Winnipeg Geothermal vehicles.
(duct work started yesterday; to be completed tomorrow)
 
Winnipeg Geothermal workers (three plus lady, not in picture).
 
Construction of primary duct.
This one will be in the crawl space and run the length of the house, supplying air from the furnace/heat pump to the other rooms.
 
HRV duct in wall of first floor bathroom.
 
HRV duct in wall between laundry and Rebecca's room.
 
Portion of stairs in back of Dave's truck.
To be installed later this afternoon - was done after we left - an important step (pun intended) in the development of the house.