May 1
Construction about to start! |
May 5
Grade beam in place |
|
|
|
|
May 12
Geothermal driller arriving |
May 16
Crawl space about to be dug |
|
|
|
|
May 18
Main floor joists are in place; stumps (in foreground) are gone. |
May 22
Main floor exterior walls in place. |
|
|
|
|
May 24
Main floor interior walls in place. |
May 27
Second floor joists and portion of upper walls in place.
(picture as of our arriving this morning). |
|
|
|
|
May 30
Most of the roof trusses are in place. |
May 31
Rear roof is being sheeted. |
|
|
|
|
June 3
Front dormers being placed; front roof starting to be sheeted. |
June 7
Front dormers and sheeting completed. |
|
|
|
|
June 9
Shingles on front of house; some windows installed. |
June 12
Shingles on rear of house; soffit on south side. |
|
|
|
|
June 14
Lots of interior activity: ducts and electrical both started. |
June 17
Siding started (between 1/3 and 1/2 done). |
|
|
|
|
June 19
More siding; well being dug (to right/North of house). |
June 21
Lots of insulating done. |
|
|
|
|
June 27
Front verandah on; 98% of drywalling done!.
We were out after supper (sun is setting in west). |
June 30
Almost all exterior work done. |
|
|
|
|
Jul 8
Septic line was put in yesterday - a bit more to do on Monday. |
Jul 10
Septic tank installed; started interior painting. |
|
|
|
|
Jul 18
High speed internet hookup; geothermal heat pump delivered.. |
Jul 20
MOVING DAY! |
|
|
|
|
Aug 2
Driveway |
|
|
|